NASA: Assessments of Major Projects

What GAO Found Most of the National Aeronautics and Space Administration’s (NASA) major projects in development reported no schedule delays or cost overruns in the last year. These projects are in the phase of building and testing their designs. Two of these 18 projects reported annual schedule delays (totaling 2 months) and three reported cost overruns (totaling $501.4 million). Similarly, the portfolio’s cumulative costs and delays increased slightly, from $4.4 billion to nearly $4.7 billion and from 13.1 years to 14 years, respectively. The Orion crew capsule accounts for over half of the major projects’ annual cost overruns and almost 75 percent of their cumulative cost overruns. Cost a.

ML Reported by Maria Lopez

NASA: Assessments of Major Projects.

The item is dated Thu, 23 Jul 2026 07:37:37 -0400.

TeamCog is carrying it as a audits report from GAO reports and testimonies RSS.

What GAO Found Most of the National Aeronautics and Space Administration’s (NASA) major projects in development reported no schedule delays or cost overruns in the last year.

These projects are in the phase of building and testing their designs.

Two of these 18 projects reported annual schedule delays (totaling 2 months) and three reported cost overruns (totaling $501.4 million).

Similarly, the portfolio’s cumulative costs and delays increased slightly, from $4.4 billion to nearly $4.7 billion and from 13.1 years to 14 years, respectively.

The Orion crew capsule accounts for over half of the major projects’ annual cost overruns and almost 75 percent of their cumulative cost overruns.