What GAO Found A Secretary of Energy memorandum directed revisions to the Department of Energy’s (DOE) construction order (known as 413.3B) to (1) allow increased delegation of approval authority for projects estimated to cost up to $300 million; and (2) limit independent reviews for projects estimated to cost between $300 million and $1 billion. As of January 2026, DOE and the National Nuclear Security Administration (NNSA) were managing 80 capital asset projects at laboratories and sites where daily operations are carried out by management and operating (M&O) contractors. The projects are collectively estimated to cost as much as $65.5 billion. Revisions could affect 66 of the ongoing pro.

ML Reported by Maria Lopez

Department of Energy: Efforts to Streamline Project Management at National Laboratories and Nuclear Sites [Reissued with revisions on Jul. 17, 2026].

The item is dated Thu, 16 Jul 2026 07:17:33 -0400.

TeamCog is carrying it as a audits report from GAO reports and testimonies RSS.

What GAO Found A Secretary of Energy memorandum directed revisions to the Department of Energy’s (DOE) construction order (known as 413.3B) to (1) allow increased delegation of approval authority for projects estimated to cost up to $300 million; and (2) limit independent reviews for projects estimated to cost between $300 million and $1 billion.

As of January 2026, DOE and the National Nuclear Security Administration (NNSA) were managing 80 capital asset projects at laboratories and sites where daily operations are carried out by management and operating (M&O) contractors.

The projects are collectively estimated to cost as much as $65.5 billion.

Revisions could affect 66 of the ongoing pro…